Omaha-based Darland Construction has begun construction on a new corporate headquarters in the city for Pinnacle Bank. Darland and Avant Architects have been working with Pinnacle Bank on this project since the early planning stages. The three-story structure will include 63,000 square feet of office space and a 19,000-square-foot underground parking garage.
The facility will house a full-service Pinnacle Bank office on the first floor and Pinnacle Bank’s corporate headquarters on the third floor. Seim Johnson, a local accounting/consulting firm, will occupy the second floor.
During the design stage, the project expanded by nearly 30 percent to accommodate the new tenant.
“The design and preconstruction planning stages were significantly extended, although the completion date remained the same,” said Darland principal Jerry Kelley. “Because of the fully-integrated approach we have taken with Avant Architects, and our detailed preconstruction process, we will achieve Pinnacle’s budget and schedule objectives.”
The 12-month construction plan specifies a May of 2011 completion date.
Sid Dinsdale, Pinnacle president, adds, “We really like the coordinated effort, all of us working together. We talked to Darland and the architect all along about how to hit our delivery date. We have a lot of confidence in Darland, because they’ve done a number of projects for us and always come through. I know we threw them some significant curves on this one, but I’ve no doubt they’ll get it done.”